Solved Question
This question was previously asked in:
IB ACIO Tire-l TEST 11 • IB ACIO Tire-l TEST
A, B, and C can complete a piece of work in 20, 30, and 60 days respectively. A works continuously, but is assisted by both B and C on every third day. In how many days will the work be compl
Answer (Detailed Solution Below)
✓
Option 1 : 15 days (Option A)
📌 Key Points & Important Facts:
The correct answer is Option 1: 15 days.